A lintel is a beam placed across the openings like doors, windows, etc. in buildings to support the load from the structure above. The width of the lintel beam is equal to the width of the wall, and the ends of it is built into the wall.

Steel lintel Installation Guide

LINTEL INSTALLATION  ESSENTIAL TIPS

  • Steel Lintels should be installed with a minimum end bearing of 150mm, bedded on mortar, and leveled along its length and across its width.
  • The masonry above the lintel should be built in accordance with BS EN 1996-2:2006.
  • Raise the inner and outer leaves simultaneously to avoid excessive eccentricity of loading, with a maximum height difference of 225mm (Masonry should be laid on a mortar bed and all perpendicular joints should be filled.)
  • Allow the mortar to cure before applying floor or roof loads (Temporary propping beneath a steel lintel is practiced to facilitate speed of construction).
  • The NHBC recommends a damp proof course (DPC) or cavity tray should be installed over all openings in external cavity walls.
  • When installing concrete floor units or other heavy components above a lintel, care should be taken to avoid shock loading and floor units should not be dragged into position. Masonry immediately above the lintel should be allowed to cure.
  • Point loads should not be applied directly onto lintel flanges. Steel Lintels should have a minimum of masonry 150mm high between the flange and the application level of any form of loading. Consult IG’s technical department if applying a point load above lintels.
  • The external lintel flange must project beyond the window/door frame and it is recommended that a flexible sealing compound is used between the underside of the lintel flange and the frame.
  • When the underside of a lintel is exposed, its appearance can be enhanced by the addition of lintel soffit cladding.
  • Do not cut lintels to length or modify them in any way without consulting an engineer.

INSTALLATION TIPS FOR CONCRETE LINTELS:

  • Recommended bearings are 100mm for openings of up to 1m, and 150mm for openings over 1m. The Minimum recommended lintel depth is 140mm in order to absorb the shock loading of a concrete floor. Precast flooring units should be laid on a mortar bed across the whole wall width and should not be dragged over supports.

INSTALLATION TIPS FOR STEEL LINTELS:

  • Inner and outer leaves supported by the lintels should be raised together to avoid excessive eccentricity of loading. In the case of cavity walls, the cavity tray should extend not less than 50mm beyond the cavity return. The minimum recommended bearing length is 150mm.
  • Composite lintels should be adequately propped during construction, at maximum centers of 1.2m. The props should not be removed until the mortar has cured.
  • For the channel, lintels ensure that the inner leaf channel is filled with well-cured masonry before work proceeds over. Masonry needs to be built tightly against the vertical section of the channel and a mortar joint added to the top of the masonry so that the loads from units above are spread evenly over the inner flange of the lintel.
  • For Rolled steel lintels a minimum bearing of 200mm is required and must be laterally restrained and adequately propped during construction at a maximum of 1.2-meter centers. For the timber frame, a tight-fitting timber batten should be placed at mid-span to help prevent any lateral deflection.

Many walls in your house will be what are called supporting walls. This clearly means they support something! This could be the walls for the rooms upstairs, the ceiling, or all the way up to the roof.

Lintels need to be inserted over every opening in a wall where the wall would be weakened by that opening. The principle is that by inserting a lintel, the weight above it is transferred to either side of it. This’s why a minimum of 150mm bearing must be allowed for the lintel to sit on the masonry on either side of the opening. Walls dimensions should be correct, and the lintel should be fully bedded on bricklaying mortar